Overview

  • Learn how to load, create and customize links connecting tasks displayed in the React Scheduler component.

  • Links are a flexible way of displaying task dependencies, highlighting the distance between events, showing follow-up actions, and connecting related tasks.

  • See how to set custom color, text, and style of links.

  • Set link properties conditionally, depending on the connected tasks, and highlight potential schedule issues.

  • Use drag and drop to create new links and a context menu to edit or delete existing links.

  • Display additional link details on hover using a dynamic tooltip.

  • The React project includes a trial version of DayPilot Pro for JavaScript (see License below).

License

Licensed for testing and evaluation purposes. Please see the license agreement included in the sample project. You can use the source code of the tutorial if you are a licensed user of DayPilot Pro for JavaScript. Buy a license.

Link Use Cases

Links are powerful visual elements that let you visualize relations between tasks in the React Scheduler UI. Let’s take a look at how they can be used in planning and scheduling applications.

Show Dependencies between Tasks

The link indicates that the first task must be completed before the second task can be started (like in the React Gantt Chart Tutorial).

Visualize Sequence of Operation

The link points to the next step in a sequence of tasks (like in the ASP.NET Core Machine Scheduling tutorial).

React Scheduler - Using Links to Visualize Sequence of Operation

Connect Multiple Representations of the Same Task

You can link the boxes representing assignments of the same task to multiple resources (like in the React Shift Scheduling tutorial).

Show Time between Tasks using Links

The links can display text above the line. You can use it to display additional description of the action or time between the connected tasks. You can find more in the ASP.NET Core Field Service Scheduling: Tasks, Routes, and Travel Time tutorial.

How to Show Links between Tasks in React Scheduler

react scheduler load links

In the React Scheduler component, you can load links using the links prop. The value needs to be an array of link data objects. The data object must specify the source and target tasks using from and to properties.

There are a couple of optional properties that you can define for links:

  • id - In some cases, it’s not necessary (e.g., if the links are generated dynamically to connect related events). If you store the links in the database or if you need to update them individually, it is necessary to specify the ID.

  • type - The default link type is "FinishToStart". If you want to create a link that connects other endpoints than the end of the first task with the start of the second task, specify the corresponding link type.

  • color - Set a custom link color.

  • text - The Finish to Start links can display a custom text above the link line.

In this React example, the Scheduler loads the initial resources, events, and links into React state. After loading, the interaction handlers modify the Scheduler’s event and link collections directly. The sample uses small async loader functions to mirror an application that loads data from an API, and it opens the timeline on the current month using DayPilot.Date.today().firstDayOfMonth().

const loadResources = async () => [
  { name: "Resource A", id: "A" },
  { name: "Resource B", id: "B" },
  { name: "Resource C", id: "C" },
  { name: "Resource D", id: "D" },
  { name: "Resource E", id: "E" },
  { name: "Resource F", id: "F" },
  { name: "Resource G", id: "G" }
];

const loadTasks = async (startDate) => [
  {
    id: 1,
    text: "Task 1",
    start: startDate.addDays(1),
    end: startDate.addDays(4),
    resource: "A"
  },
  {
    id: 2,
    text: "Task 2",
    start: startDate.addDays(8),
    end: startDate.addDays(15),
    resource: "B",
    barColor: "#38761d",
    barBackColor: "#93c47d"
  },
  {
    id: 3,
    text: "Task 3",
    start: startDate.addDays(3),
    end: startDate.addDays(9),
    resource: "D",
    barColor: "#f1c232",
    barBackColor: "#f1c232"
  },
  {
    id: 4,
    text: "Task 4",
    start: startDate.addDays(10),
    end: startDate.addDays(16),
    resource: "F",
    barColor: "#cc0000",
    barBackColor: "#ea9999"
  }
];

const loadLinks = async () => [
  { id: 1, from: 1, to: 2 },
  { id: 2, from: 1, to: 3 },
  { id: 3, from: 3, to: 4 }
];

const Scheduler = () => {
  // ...
  const [startDate] = useState(() => DayPilot.Date.today().firstDayOfMonth());
  const [resources, setResources] = useState([]);
  const [events, setEvents] = useState([]);
  const [links, setLinks] = useState([]);
  const [isLoading, setIsLoading] = useState(true);

  const days = startDate.daysInMonth();

  useEffect(() => {
    Promise.all([
      loadResources(),
      loadTasks(startDate),
      loadLinks()
    ]).then(([loadedResources, loadedEvents, loadedLinks]) => {
      setResources(loadedResources);
      setEvents(loadedEvents);
      setLinks(loadedLinks);
      setIsLoading(false);
    });
  }, [startDate]);

  // ...
};

The loaded links array is passed directly to the Scheduler using the links prop:

<DayPilotScheduler
  timeHeaders={[{ groupBy: "Month" }, { groupBy: "Day", format: "d" }]}
  scale="Day"
  startDate={startDate}
  days={days}
  events={events}
  resources={resources}
  links={links}
  timeRangeSelectedHandling="Enabled"
  linkCreateHandling="Update"
  onBeforeLinkRender={onBeforeLinkRender}
  onTimeRangeSelected={onTimeRangeSelected}
  onLinkCreate={onLinkCreate}
  onLinkClick={onLinkClick}
  contextMenuLink={contextMenuLink}
  linkBubble={linkBubble}
  controlRef={setScheduler}
/>

How to Set Links Properties Dynamically (Color, Text, CSS Class)

react scheduler invalid link

There is a special event handler called onBeforeLinkRender that allows you to set link properties dynamically, depending on custom field values or the connected events.

The following onBeforeLinkRender handler checks FinishToStart links and compares the end date of the source task with the start date of the target task. If the subsequent task begins too early, it changes the link style to "dotted" and adds the text "Invalid":

const onBeforeLinkRender = (args) => {
  const source = args.from;
  const target = args.to;
  const type = args.data.type || "FinishToStart";

  if (type === "FinishToStart" && source.end() > target.start()) {
    args.data.style = "dotted";
    args.data.text = "Invalid";
  }
};

This event handler is attached to the Scheduler using the onBeforeLinkRender attribute:

<DayPilotScheduler
  // ...
  onBeforeLinkRender={onBeforeLinkRender}
  // ...
/>

How to Create Links using Drag and Drop

react scheduler create link

To enable creation of links using drag and drop in the React Scheduler component, it is necessary to enable this option using the linkCreateHandling prop. In most cases, you will also want to define the onLinkCreate handler and use it to save the new link in the database using an HTTP call to the server. This sample stores changes in the browser only; reloading the page restores the initial data.

Our onLinkCreate handler checks the link type and opens a modal dialog for entering link description if the link type is "FinishToStart".

You can also see that the event handler cancels the default action using args.preventDefault(), creates a temporary gray link to highlight the future position, and asks for the text. It uses the Scheduler instance supplied by controlRef={setScheduler}; onLinkCreate arguments provide the endpoints and type, but no control property.

If you cancel the modal dialog, the temporary link is removed and no permanent link is created. For other link types, the handler returns without canceling the default action, so the Scheduler creates the link without a description prompt.

const onLinkCreate = async (args) => {
  if (args.type !== "FinishToStart") {
    return;
  }

  args.preventDefault();

  const tempLink = {
    from: args.from,
    to: args.to,
    id: DayPilot.guid(),
    type: args.type,
    color: "#cccccc"
  };

  scheduler.links.add(tempLink);

  const modal = await DayPilot.Modal.prompt("Link description:", "Link 1");

  scheduler.links.remove(tempLink);

  if (modal.canceled) {
    return;
  }

  scheduler.links.add({
    from: args.from,
    to: args.to,
    id: DayPilot.guid(),
    type: args.type,
    text: modal.result
  });
};

The handler is active when linkCreateHandling is set to "Update":

<DayPilotScheduler
  // ...
  linkCreateHandling="Update"
  // ...
  onLinkCreate={onLinkCreate}
  // ...
/>

How to Create Context Menu for Deleting and Editing Task Links

react scheduler link menu

To provide additional actions related to an existing link, we add a context menu using the contextMenuLink prop.

The context menu defines two items:

  • Delete

  • Properties…

The “Delete” item removes the link from the Scheduler UI.

The “Properties…” item opens a modal dialog that lets you edit link properties, such as type, color, and text.

const contextMenuLink = useMemo(() => new DayPilot.Menu({
  items: [
    { text: "Delete", onClick: (args) => scheduler?.links.remove(args.source) },
    { text: "-" },
    { text: "Properties...", onClick: (args) => editLink(args.source.data) }
  ]
}), [editLink, scheduler]);

JSX:

<DayPilotScheduler
  ...
  contextMenuLink={contextMenuLink}
  ...
/>

How to Show Bubble with Link Details on Hover

react scheduler link bubble

The React Scheduler component allows displaying a custom tooltip when hovering over a link with a mouse cursor.

The tooltip can be defined using the linkBubble prop. The value is a DayPilot.Bubble object that specifies the tooltip appearance and behavior.

Since there is no default text that the tooltip would display, we use the onLoad event to define the content dynamically as HTML. Our onLoad handler looks up the tasks connected by the link and shows the source and target task names. It escapes the names before inserting them into the tooltip HTML.

const linkBubble = useMemo(() => new DayPilot.Bubble({
  position: "Mouse",
  onLoad: (args) => {
    if (!scheduler) {
      return;
    }

    const link = args.source;
    const source = scheduler.events.find(link.data.from);
    const target = scheduler.events.find(link.data.to);

    if (source && target) {
      args.html = `Link from <b>${DayPilot.Util.escapeHtml(source.data.text)}</b> to <b>${DayPilot.Util.escapeHtml(target.data.text)}</b>`;
    }
  }
}), [scheduler]);

Full Source Code

Here is the full source code of our React Scheduler component that shows links connecting the tasks.

import {useCallback, useEffect, useMemo, useState} from "react";
import {DayPilot, DayPilotScheduler} from "daypilot-pro-react";

const linkForm = [
  { name: "Source", id: "source", disabled: true },
  { name: "Target", id: "target", disabled: true },
  {
    name: "Type",
    id: "type",
    type: "select",
    options: [
      { name: "Finish to Start", id: "FinishToStart" },
      { name: "Start to Start", id: "StartToStart" },
      { name: "Finish to Finish", id: "FinishToFinish" },
      { name: "Start to Finish", id: "StartToFinish" }
    ]
  },
  {
    name: "Color",
    id: "color",
    type: "select",
    options: [
      { name: "Gray", id: "#cccccc" },
      { name: "Green", id: "#38761d" },
      { name: "Yellow", id: "#f1c232" },
      { name: "Red", id: "#cc0000" }
    ]
  },
  { name: "Text", id: "text" }
];

const loadResources = async () => [
  { name: "Resource A", id: "A" },
  { name: "Resource B", id: "B" },
  { name: "Resource C", id: "C" },
  { name: "Resource D", id: "D" },
  { name: "Resource E", id: "E" },
  { name: "Resource F", id: "F" },
  { name: "Resource G", id: "G" }
];

const loadTasks = async (startDate) => [
  {
    id: 1,
    text: "Task 1",
    start: startDate.addDays(1),
    end: startDate.addDays(4),
    resource: "A"
  },
  {
    id: 2,
    text: "Task 2",
    start: startDate.addDays(8),
    end: startDate.addDays(15),
    resource: "B",
    barColor: "#38761d",
    barBackColor: "#93c47d"
  },
  {
    id: 3,
    text: "Task 3",
    start: startDate.addDays(3),
    end: startDate.addDays(9),
    resource: "D",
    barColor: "#f1c232",
    barBackColor: "#f1c232"
  },
  {
    id: 4,
    text: "Task 4",
    start: startDate.addDays(10),
    end: startDate.addDays(16),
    resource: "F",
    barColor: "#cc0000",
    barBackColor: "#ea9999"
  }
];

const loadLinks = async () => [
  { id: 1, from: 1, to: 2 },
  { id: 2, from: 1, to: 3 },
  { id: 3, from: 3, to: 4 }
];

const Scheduler = () => {
  const [scheduler, setScheduler] = useState(null);
  const [startDate] = useState(() => DayPilot.Date.today().firstDayOfMonth());
  const [resources, setResources] = useState([]);
  const [events, setEvents] = useState([]);
  const [links, setLinks] = useState([]);
  const [isLoading, setIsLoading] = useState(true);

  const days = startDate.daysInMonth();

  useEffect(() => {
    Promise.all([
      loadResources(),
      loadTasks(startDate),
      loadLinks()
    ]).then(([loadedResources, loadedEvents, loadedLinks]) => {
      setResources(loadedResources);
      setEvents(loadedEvents);
      setLinks(loadedLinks);
      setIsLoading(false);
    });
  }, [startDate]);

  const onTimeRangeSelected = async (args) => {
    const modal = await DayPilot.Modal.prompt("Create a new task:", "Task 1");
    args.control.clearSelection();

    if (modal.canceled) {
      return;
    }

    args.control.events.add({
      start: args.start,
      end: args.end,
      id: DayPilot.guid(),
      resource: args.resource,
      text: modal.result
    });
  };

  const onLinkCreate = async (args) => {
    if (args.type !== "FinishToStart") {
      return;
    }

    args.preventDefault();

    const tempLink = {
      from: args.from,
      to: args.to,
      id: DayPilot.guid(),
      type: args.type,
      color: "#cccccc"
    };

    scheduler.links.add(tempLink);

    const modal = await DayPilot.Modal.prompt("Link description:", "Link 1");

    scheduler.links.remove(tempLink);

    if (modal.canceled) {
      return;
    }

    scheduler.links.add({
      from: args.from,
      to: args.to,
      id: DayPilot.guid(),
      type: args.type,
      text: modal.result
    });
  };

  const onBeforeLinkRender = (args) => {
    const source = args.from;
    const target = args.to;
    const type = args.data.type || "FinishToStart";

    if (type === "FinishToStart" && source.end() > target.start()) {
      args.data.style = "dotted";
      args.data.text = "Invalid";
    }
  };

  const editLink = useCallback(async (link) => {
    if (!scheduler) {
      return;
    }

    const source = scheduler.events.find(link.from);
    const target = scheduler.events.find(link.to);

    const data = {
      ...link,
      source: source?.data.text,
      target: target?.data.text,
      type: link.type || "FinishToStart",
      color: link.color || "#cc0000"
    };

    const modal = await DayPilot.Modal.form(linkForm, data);

    if (modal.canceled) {
      return;
    }

    scheduler.links.update(modal.result);
  }, [scheduler]);

  const onLinkClick = (args) => {
    editLink(args.link.data);
  };

  const contextMenuLink = useMemo(() => new DayPilot.Menu({
    items: [
      { text: "Delete", onClick: (args) => scheduler?.links.remove(args.source) },
      { text: "-" },
      { text: "Properties...", onClick: (args) => editLink(args.source.data) }
    ]
  }), [editLink, scheduler]);

  const linkBubble = useMemo(() => new DayPilot.Bubble({
    position: "Mouse",
    onLoad: (args) => {
      if (!scheduler) {
        return;
      }

      const link = args.source;
      const source = scheduler.events.find(link.data.from);
      const target = scheduler.events.find(link.data.to);

      if (source && target) {
        args.html = `Link from <b>${DayPilot.Util.escapeHtml(source.data.text)}</b> to <b>${DayPilot.Util.escapeHtml(target.data.text)}</b>`;
      }
    }
  }), [scheduler]);

  return (
    <div aria-busy={isLoading}>
      <DayPilotScheduler
        timeHeaders={[{ groupBy: "Month" }, { groupBy: "Day", format: "d" }]}
        scale="Day"
        startDate={startDate}
        days={days}
        events={events}
        resources={resources}
        links={links}
        timeRangeSelectedHandling="Enabled"
        linkCreateHandling="Update"
        onBeforeLinkRender={onBeforeLinkRender}
        onTimeRangeSelected={onTimeRangeSelected}
        onLinkCreate={onLinkCreate}
        onLinkClick={onLinkClick}
        contextMenuLink={contextMenuLink}
        linkBubble={linkBubble}
        controlRef={setScheduler}
      />
    </div>
  );
};

export default Scheduler;

You can download the React project using the link at the top of the tutorial.